Project Description

Design, supply, fabrication, and paint of 40 storage tanks at 3.6m diameter by 10m high.

Project Challenges

The shear volume of this order presented many challenges. With an assembly line production plan we produced all the tanks in 26 weeks.

Our automatic tank welding equipment for welding the circumferential and vertical seams produced excellent results and helped meet production quotas.

Our state of the art surface preparation and coating facilities produced quality products to specifications.